English translation of the original Swedish diary entry. Swedish original below. Plans and observations belong to the time of writing.
The detailed design continues. Final architectural and structural drawings are being prepared: Palmatin is working on the house, Fredrik on the overall design, and Niklas on the structure.

A surveying level arrived today, and I tried taking some measurements. It measures heights, angles and distances. We will measure more once the bedrock is exposed, but the measurements we took with a water level in 2013 seem reasonably accurate.
Digging starts on Monday. The soil will be stripped off the bedrock so we can see whether anything needs blasting. Exciting!